Наверх

Transneft Urals, JSC, has performed the scheduled works at petroleum product trunk pipelines

Date of publication: 29 January 2018 Print

Transneft Urals has performed the scheduled works at Ufa – West (UW), Salavat – Ufa, Ufa – Omsk and Ufa – Petropavlovsk petroleum products trunk pipelines (PPTP).

Medium repair of four line gate valves was performed at UW PPTP (section Subkhankulovo – Priboy), three defects were eliminated on industrial pipelines of Georgievka-PP line operation dispatcher station (LODS). Three narrowings were cut at Salavat – Ufa PPTP, medium repair of a gate valve was performed at industrial pipelines of Salavat-PP LODS.

Ultrasonic flowmeters were tied in at Ufa – Omsk PPTP (section Omsk – Petropavlovsk) and Ufa – Petropavlovsk PPTP (section Petropavlovsk – Khokhly), they will secure increasing accuracy of the pumped petroleum products metering. Dismantling of a temporary PIG trap was performed at Ufa – Petropavlovsk PPTP, seven defects were eliminated.

Business units of Tuymazy, Cherkassy, Chelyabinsk, Kurgan and Arlan Oil Pipeline Directorates of Transneft Urals participated in the scheduled works. The scheduled works have been performed to the full extent; petroleum products transportation is restored within the appropriate periods.